Tuesday, July 28, 2009

Upper floor completed



Upper floor frame has been completed, including the front section for kitchen, study, and main entrance porch. There is nothing underneath this front section because of the sloping land. However, they did enough cut and fill to fit a small living room underneath the front porch. This will have to be built later as it's not included in the builder's contract.



They use a different steel structure for the upper floor front section as it has no indoor space underneath. i.e, no need for frames to hang ceiling on or to run pipes and cables between the upper floor and the ceiling below it.



It's quite amazing that most of the sub-floors and the frame installation thus far were done by these two guys. There was a third guy when they worked on the lower sub-floor, but for the past three days the works were apparently done by these two.